First National
Bank of the South
Greenville, SC
Construction Project Status Report |
| Updated |
01-12-07 |
Week Ending |
01-13-07 |
| Architect # |
0601 |
Weather |
Cold / Sunny |
| Roebuck Buildings Job# |
5281 |
Reporter |
Darryl |
| 1. General Requirements |
N/A |
| 2. Site Construction |
N/A |
| 3. Concrete |
pour the 2nd floor next week and around
columns |
| 4. Masonry |
N/A |
| 5. Metals |
Structural steel 80% set, have decking and
stairs left also final tightening |
| 6. Woods & Plastics |
N/A |
| 7. Thermal & Moisture Protection |
N/A |
| 8. Doors & Windows |
N/A |
| 9. Finishes |
Metal studs should start next week |
| 10. Specialties |
N/A |
| 11. Equipment |
N/A |
| 12. Furnishings |
N/A |
| 13. Special Construction |
N/A |
| 14. Conveying Systems |
N/A |
| 15. Mechanical |
N/A |
| 16. Electrical |
N/A |
| |
| Progress Meetings |
To be scheduled |
| Architect Action Items |
|
| Subcontractor Action Items |
Still need temp power hooked up, let's just
hook it up to the pole. |
| Owner Action Items |
none |
|
 |
View from Trailer |
|
 |
|
Drive thru steel |
|
 |
|
1st Floor |
|
 |
|
Bar Joists |
|
 |
|
Back entrance |
|
|