Construction Project Status Report |
| Updated |
02-22-07 |
Week Ending |
02-24-07 |
| Architect # |
0601 |
Weather |
Sunny and rain |
| Roebuck Buildings Job# |
5281 |
Reporter |
Darryl |
| 1. General Requirements |
N/A |
| 2. Site Construction |
N/A |
| 3. Concrete |
poured column cut outs |
| 4. Masonry |
elevator shaft done |
| 5. Metals |
stairs are left |
| 6. Woods & Plastics |
N/A |
| 7. Thermal & Moisture Protection |
trusses delivered yesterday and today |
| 8. Doors & Windows |
N/A |
| 9. Finishes |
1st floor 90% framed, all exterior walls and
track on the 2nd floor |
| 10. Specialties |
N/A |
| 11. Equipment |
N/A |
| 12. Furnishings |
N/A |
| 13. Special Construction |
N/A |
| 14. Conveying Systems |
N/A |
| 15. Mechanical |
plumbing rough in starts Monday |
| 16. Electrical |
rough in starting Monday |
| |
| Progress Meetings |
To be scheduled |
| Architect Action Items |
|
| Subcontractor Action Items |
none |
| Owner Action Items |
still need the specs for the drive thru
tellers and night deposit boxes |
|
 |