First National
Bank of the South
Greenville, SC
Construction Project Status Report |
| Updated |
12-15-06 |
Week Ending |
12-16-06 |
| Architect # |
0601 |
Weather |
Cold / Sunny |
| Roebuck Buildings Job# |
5281 |
Reporter |
Darryl |
| 1. General Requirements |
N/A |
| 2. Site Construction |
Dug elevator pit |
| 3. Concrete |
Poured more footings |
| 4. Masonry |
Pad edge complete |
| 5. Metals |
Structural steel has a delivery
date of 1/8/07 |
| 6. Woods & Plastics |
N/A |
| 7. Thermal & Moisture Protection |
N/A |
| 8. Doors & Windows |
N/A |
| 9. Finishes |
N/A |
| 10. Specialties |
N/A |
| 11. Equipment |
N/A |
| 12. Furnishings |
N/A |
| 13. Special Construction |
N/A |
| 14. Conveying Systems |
N/A |
| 15. Mechanical |
Plumbing underground inspected |
| 16. Electrical |
Electrical underground being installed |
| |
| Progress Meetings |
To be scheduled |
| Architect Action Items |
|
| Subcontractor Action Items |
Still need temp power hooked up |
| Owner Action Items |
none |
|
 |
North Wall |
|
 |
|
Underground plumbing |
|
 |
|
west wall |
|
 |
|
NW corner |
|
 |
|
From Trailer Steps |
|
|