Project Start Date: Wed 11/8/06
Project Finish Date: Wed 5/2/07
Name | Scheduled_Work | Percent_Work_Complete | Duration | Start_Date | Finish_Date | Resource_Names |
|---|---|---|---|---|---|---|
Grading | 80 hrs | 100% | 8 days | Mon 10/16/06 | Tue 10/31/06 | PAR |
PAR | 80 hrs | 100% | Mon 10/16/06 | Tue 10/31/06 | PAR | |
Mobilization | 10 hrs | 100% | 1 day | Wed 11/8/06 | Thu 11/9/06 | RB |
RB | 10 hrs | 100% | Wed 11/8/06 | Thu 11/9/06 | RB | |
Footings | 80 hrs | 100% | 38.6 days | Mon 11/13/06 | Sat 2/3/07 | |
layout | 10 hrs | 100% | 1 day | Mon 11/13/06 | Tue 11/14/06 | RB |
RB | 10 hrs | 100% | Mon 11/13/06 | Tue 11/14/06 | RB | |
dig footers | 20 hrs | 100% | 2 days | Tue 11/14/06 | Thu 11/16/06 | RB |
RB | 20 hrs | 100% | Tue 11/14/06 | Thu 11/16/06 | RB | |
rebar | 10 hrs | 100% | 1 day | Thu 11/16/06 | Mon 11/20/06 | RB |
RB | 10 hrs | 100% | Thu 11/16/06 | Mon 11/20/06 | RB | |
rebar testing | 10 hrs | 100% | 1 day | Tue 11/21/06 | Wed 11/22/06 | SM&E |
SM&E | 10 hrs | 100% | Tue 11/21/06 | Wed 11/22/06 | SM&E | |
set anchor bolts | 10 hrs | 100% | 1 day | Tue 11/21/06 | Wed 11/22/06 | RB |
RB | 10 hrs | 100% | Tue 11/21/06 | Wed 11/22/06 | RB | |
Footer Inspection | 0 hrs | 100% | 1 day | Thu 2/1/07 | Sat 2/3/07 | |
pour footings | 10 hrs | 100% | 1 day | Wed 11/22/06 | Thu 11/23/06 | RB |
RB | 10 hrs | 100% | Wed 11/22/06 | Thu 11/23/06 | RB | |
concrete testing | 10 hrs | 100% | 1 day | Wed 11/22/06 | Thu 11/23/06 | SM&E |
SM&E | 10 hrs | 100% | Wed 11/22/06 | Thu 11/23/06 | SM&E | |
Slab on grade | 110 hrs | 100% | 33.6 days | Thu 11/23/06 | Mon 2/5/07 | |
elevator jack hole | 20 hrs | 100% | 2 days | Thu 11/23/06 | Tue 11/28/06 | Tysen Krupp |
Tysen Krupp | 20 hrs | 100% | Thu 11/23/06 | Tue 11/28/06 | Tysen Krupp | |
block edge | 20 hrs | 100% | 2 days | Mon 11/27/06 | Wed 11/29/06 | Pride masonry |
Pride masonry | 20 hrs | 100% | Mon 11/27/06 | Wed 11/29/06 | Pride masonry | |
stone base | 10 hrs | 100% | 1 day | Wed 11/29/06 | Thu 11/30/06 | RB |
RB | 10 hrs | 100% | Wed 11/29/06 | Thu 11/30/06 | RB | |
underground plumbing | 30 hrs | 100% | 3 days | Thu 11/23/06 | Thu 11/30/06 | Upstate |
Upstate | 30 hrs | 100% | Thu 11/23/06 | Thu 11/30/06 | Upstate | |
underground electrical | 20 hrs | 100% | 2 days | Thu 11/23/06 | Tue 11/28/06 | Port City |
Port City | 20 hrs | 100% | Thu 11/23/06 | Tue 11/28/06 | Port City | |
poly and wire | 10 hrs | 100% | 1 day | Thu 11/30/06 | Mon 12/4/06 | RB |
RB | 10 hrs | 100% | Thu 11/30/06 | Mon 12/4/06 | RB | |
Slab Inspection | 0 hrs | 100% | 1 day | Thu 2/1/07 | Sat 2/3/07 | |
pour slab | 0 hrs | 100% | 1 day | Sat 2/3/07 | Mon 2/5/07 | |
Structural Steel | 110 hrs | 100% | 11 days | Thu 12/7/06 | Mon 1/1/07 | |
delivery | 10 hrs | 100% | 1 day | Thu 12/7/06 | Mon 12/11/06 | SC Steel |
SC Steel | 10 hrs | 100% | Thu 12/7/06 | Mon 12/11/06 | SC Steel | |
erection | 90 hrs | 100% | 9 days | Mon 12/11/06 | Thu 12/28/06 | P&H erectors |
P&H erectors | 90 hrs | 100% | Mon 12/11/06 | Thu 12/28/06 | P&H erectors | |
steel testing | 10 hrs | 100% | 1 day | Thu 12/28/06 | Mon 1/1/07 | SM&E |
SM&E | 10 hrs | 100% | Thu 12/28/06 | Mon 1/1/07 | SM&E | |
Slab on deck | 10 hrs | 100% | 16.4 days | Mon 1/1/07 | Mon 2/5/07 | |
wire and screeds | 10 hrs | 100% | 1 day | Mon 1/1/07 | Tue 1/2/07 | RB |
RB | 10 hrs | 100% | Mon 1/1/07 | Tue 1/2/07 | RB | |
pour | 0 hrs | 0% | 1 day | Sat 2/3/07 | Mon 2/5/07 | |
Exterior walls | 100 hrs | 0% | 6.8 days | Thu 2/1/07 | Wed 2/14/07 | |
framing | 50 hrs | 0% | 5 days | Mon 2/5/07 | Wed 2/14/07 | Cedco |
Cedco | 50 hrs | 0% | Mon 2/5/07 | Wed 2/14/07 | Cedco | |
sheeting | 50 hrs | 0% | 5 days | Thu 2/1/07 | Mon 2/12/07 | Cedco |
Cedco | 50 hrs | 0% | Thu 2/1/07 | Mon 2/12/07 | Cedco | |
Trusses/roof system | 200 hrs | 0% | 17.8 days | Wed 2/21/07 | Mon 4/2/07 | |
delivery | 10 hrs | 0% | 1 day | Wed 2/21/07 | Thu 2/22/07 | Stark steel |
Stark steel | 10 hrs | 0% | Wed 2/21/07 | Thu 2/22/07 | Stark steel | |
set trusses | 60 hrs | 0% | 6 days | Thu 2/22/07 | Wed 3/7/07 | RB |
RB | 60 hrs | 0% | Thu 2/22/07 | Wed 3/7/07 | RB | |
roof sheating | 80 hrs | 0% | 8 days | Mon 3/5/07 | Tue 3/20/07 | RB |
RB | 80 hrs | 0% | Mon 3/5/07 | Tue 3/20/07 | RB | |
roofing | 50 hrs | 0% | 5 days | Wed 3/21/07 | Mon 4/2/07 | Grier roofing |
Grier roofing | 50 hrs | 0% | Wed 3/21/07 | Mon 4/2/07 | Grier roofing | |
Storefront | 100 hrs | 0% | 10 days | Mon 2/12/07 | Mon 3/5/07 | Piedmont glass |
Piedmont glass | 100 hrs | 0% | Mon 2/12/07 | Mon 3/5/07 | Piedmont glass | |
Brickwork | 200 hrs | 0% | 20 days | Mon 3/5/07 | Tue 4/17/07 | Pride masonry |
Pride masonry | 200 hrs | 0% | Mon 3/5/07 | Tue 4/17/07 | Pride masonry | |
Brickwork inspection | 10 hrs | 0% | 1 day | Tue 4/17/07 | Wed 4/18/07 | SM&E |
SM&E | 10 hrs | 0% | Tue 4/17/07 | Wed 4/18/07 | SM&E | |
Interior walls | 380 hrs | 0% | 19 days | Thu 2/1/07 | Tue 3/13/07 | |
framing | 60 hrs | 0% | 6 days | Wed 2/14/07 | Tue 2/27/07 | Cedco |
Cedco | 60 hrs | 0% | Wed 2/14/07 | Tue 2/27/07 | Cedco | |
elevator shaft | 80 hrs | 0% | 8 days | Mon 2/12/07 | Wed 2/28/07 | Pride masonry |
Pride masonry | 80 hrs | 0% | Mon 2/12/07 | Wed 2/28/07 | Pride masonry | |
elctrical rough-in | 40 hrs | 0% | 4 days | Thu 2/1/07 | Wed 2/7/07 | Port City |
Port City | 40 hrs | 0% | Thu 2/1/07 | Wed 2/7/07 | Port City | |
plumbing rough-in | 100 hrs | 0% | 10 days | Thu 2/1/07 | Wed 2/21/07 | Upstate |
Upstate | 100 hrs | 0% | Thu 2/1/07 | Wed 2/21/07 | Upstate | |
hvac rough-in | 10 hrs | 0% | 1 day | Thu 2/1/07 | Sat 2/3/07 | Ivestor |
Ivestor | 10 hrs | 0% | Thu 2/1/07 | Sat 2/3/07 | Ivestor | |
inwall inspection | 10 hrs | 0% | 1 day | Wed 2/21/07 | Thu 2/22/07 | County Inspection |
County Inspection | 10 hrs | 0% | Wed 2/21/07 | Thu 2/22/07 | County Inspection | |
sheeting | 80 hrs | 0% | 8 days | Thu 2/22/07 | Tue 3/13/07 | Cedco |
Cedco | 80 hrs | 0% | Thu 2/22/07 | Tue 3/13/07 | Cedco | |
Ceiling Grid | 30 hrs | 0% | 3 days | Tue 3/13/07 | Tue 3/20/07 | Cedco |
Cedco | 30 hrs | 0% | Tue 3/13/07 | Tue 3/20/07 | Cedco | |
Electric | 180 hrs | 0% | 18 days | Thu 2/8/07 | Tue 3/20/07 | Port City |
Port City | 180 hrs | 0% | Thu 2/8/07 | Tue 3/20/07 | Port City | |
Plumbing | 130 hrs | 0% | 13 days | Wed 2/21/07 | Wed 3/21/07 | Upstate |
Upstate | 130 hrs | 0% | Wed 2/21/07 | Wed 3/21/07 | Upstate | |
HVAC | 230 hrs | 0% | 23 days | Sat 2/3/07 | Thu 3/22/07 | Ivestor |
Ivestor | 230 hrs | 0% | Sat 2/3/07 | Thu 3/22/07 | Ivestor | |
Above Ceiling inspection | 20 hrs | 0% | 2 days | Mon 3/26/07 | Wed 3/28/07 | County Inspection |
County Inspection | 20 hrs | 0% | Mon 3/26/07 | Wed 3/28/07 | County Inspection | |
Exterior finishes | 60 hrs | 0% | 6 days | Tue 3/20/07 | Mon 4/2/07 | |
Curbing | 20 hrs | 0% | 2 days | Tue 3/20/07 | Thu 3/22/07 | PAR |
PAR | 20 hrs | 0% | Tue 3/20/07 | Thu 3/22/07 | PAR | |
sidewalks | 40 hrs | 0% | 4 days | Mon 3/26/07 | Mon 4/2/07 | RB |
RB | 40 hrs | 0% | Mon 3/26/07 | Mon 4/2/07 | RB | |
aspalt paving | 0 hrs | 0% | 2 days | Mon 3/26/07 | Wed 3/28/07 | |
Elevator | 170 hrs | 0% | 17 days | Tue 3/20/07 | Wed 4/25/07 | |
elevator install | 160 hrs | 0% | 16 days | Tue 3/20/07 | Tue 4/24/07 | Tysen Krupp |
Tysen Krupp | 160 hrs | 0% | Tue 3/20/07 | Tue 4/24/07 | Tysen Krupp | |
elevator inspection | 10 hrs | 0% | 1 day | Tue 4/24/07 | Wed 4/25/07 | State Inspector |
State Inspector | 10 hrs | 0% | Tue 4/24/07 | Wed 4/25/07 | State Inspector | |
Paint | 90 hrs | 0% | 9 days | Tue 3/13/07 | Mon 4/2/07 | B&B Painting |
B&B Painting | 90 hrs | 0% | Tue 3/13/07 | Mon 4/2/07 | B&B Painting | |
Millwork | 50 hrs | 0% | 5 days | Thu 3/1/07 | Tue 3/13/07 | Sawyer Cabinets |
Sawyer Cabinets | 50 hrs | 0% | Thu 3/1/07 | Tue 3/13/07 | Sawyer Cabinets | |
Ceiling Tile | 30 hrs | 0% | 3 days | Tue 4/3/07 | Mon 4/9/07 | Cedco |
Cedco | 30 hrs | 0% | Tue 4/3/07 | Mon 4/9/07 | Cedco | |
Building Finishes | 410 hrs | 0% | 17 days | Tue 3/13/07 | Wed 4/18/07 | RB |
RB | 170 hrs | 0% | Tue 3/13/07 | Wed 4/18/07 | RB | |
Hard tile | 80 hrs | 0% | 8 days | Tue 3/13/07 | Thu 3/29/07 | Tileco |
Tileco | 80 hrs | 0% | Tue 3/13/07 | Thu 3/29/07 | Tileco | |
carpet/soft tile | 80 hrs | 0% | 8 days | Tue 4/3/07 | Wed 4/18/07 | Hodge |
Hodge | 80 hrs | 0% | Tue 4/3/07 | Wed 4/18/07 | Hodge | |
molding | 80 hrs | 0% | 8 days | Tue 4/3/07 | Wed 4/18/07 | RB |
RB | 80 hrs | 0% | Tue 4/3/07 | Wed 4/18/07 | RB | |
Punchlist | 50 hrs | 0% | 5 days | Thu 4/19/07 | Tue 5/1/07 | all subs |
all subs | 50 hrs | 0% | Thu 4/19/07 | Tue 5/1/07 | all subs | |
Final Inspection | 10 hrs | 0% | 1 day | Tue 5/1/07 | Wed 5/2/07 | County Inspection |
County Inspection | 10 hrs | 0% | Tue 5/1/07 | Wed 5/2/07 | County Inspection |