Project Start Date: Wed 1/31/07
Project Finish Date: Wed 4/11/07

Task_Table1

Name
Scheduled_WorkPercent_Work_CompleteDurationStart_DateFinish_DateResource_Names
Plumbing rough-in
0 hrs0%14 daysWed 1/31/07Mon 2/19/07 
Electrical rough in
0 hrs0%21 daysWed 1/31/07Wed 2/28/07 
HVAC rough in
0 hrs0%14 daysWed 1/31/07Mon 2/19/07 
Move existing units (hvac)
0 hrs100%6 daysMon 2/5/07Mon 2/12/07 
Cut in Connector
0 hrs0%4 daysTue 2/13/07Fri 2/16/07 
connector footers
0 hrs100%3 daysMon 2/19/07Wed 2/21/07 
Connector steel
0 hrs100%2 daysThu 2/22/07Fri 2/23/07 
Connector trusses
0 hrs0%5 daysMon 2/26/07Fri 3/2/07 
shingles/roofing
0 hrs100%8 daysWed 1/31/07Fri 2/9/07 
roof/shingle connector
0 hrs0%1 dayMon 3/5/07Mon 3/5/07 
exterior masonry
0 hrs0%30 daysWed 1/31/07Tue 3/13/07 
drywall
0 hrs0%22 daysMon 2/12/07Tue 3/13/07 
building finishes
0 hrs0%14 daysMon 3/5/07Thu 3/22/07 
millwork
0 hrs0%5 daysMon 3/5/07Fri 3/9/07 
acoustical ceiling
0 hrs0%10 daysMon 3/12/07Fri 3/23/07 
Paint
0 hrs0%25 daysMon 2/26/07Fri 3/30/07 
Flooring
0 hrs0%5 daysMon 3/26/07Fri 3/30/07 
Punchlist/ demobilize
0 hrs0%8 daysMon 4/2/07Wed 4/11/07 
curb/asphalt
0 hrs0%8 daysWed 3/14/07Fri 3/23/07 
stucco
0 hrs0%14 daysTue 3/6/07Fri 3/23/07