Project Start Date: Wed 1/31/07
Project Finish Date: Wed 4/11/07
Name | Scheduled_Work | Percent_Work_Complete | Duration | Start_Date | Finish_Date | Resource_Names |
|---|---|---|---|---|---|---|
Plumbing rough-in | 0 hrs | 0% | 14 days | Wed 1/31/07 | Mon 2/19/07 | |
Electrical rough in | 0 hrs | 0% | 21 days | Wed 1/31/07 | Wed 2/28/07 | |
HVAC rough in | 0 hrs | 0% | 14 days | Wed 1/31/07 | Mon 2/19/07 | |
Move existing units (hvac) | 0 hrs | 100% | 6 days | Mon 2/5/07 | Mon 2/12/07 | |
Cut in Connector | 0 hrs | 0% | 4 days | Tue 2/13/07 | Fri 2/16/07 | |
connector footers | 0 hrs | 100% | 3 days | Mon 2/19/07 | Wed 2/21/07 | |
Connector steel | 0 hrs | 100% | 2 days | Thu 2/22/07 | Fri 2/23/07 | |
Connector trusses | 0 hrs | 0% | 5 days | Mon 2/26/07 | Fri 3/2/07 | |
shingles/roofing | 0 hrs | 100% | 8 days | Wed 1/31/07 | Fri 2/9/07 | |
roof/shingle connector | 0 hrs | 0% | 1 day | Mon 3/5/07 | Mon 3/5/07 | |
exterior masonry | 0 hrs | 0% | 30 days | Wed 1/31/07 | Tue 3/13/07 | |
drywall | 0 hrs | 0% | 22 days | Mon 2/12/07 | Tue 3/13/07 | |
building finishes | 0 hrs | 0% | 14 days | Mon 3/5/07 | Thu 3/22/07 | |
millwork | 0 hrs | 0% | 5 days | Mon 3/5/07 | Fri 3/9/07 | |
acoustical ceiling | 0 hrs | 0% | 10 days | Mon 3/12/07 | Fri 3/23/07 | |
Paint | 0 hrs | 0% | 25 days | Mon 2/26/07 | Fri 3/30/07 | |
Flooring | 0 hrs | 0% | 5 days | Mon 3/26/07 | Fri 3/30/07 | |
Punchlist/ demobilize | 0 hrs | 0% | 8 days | Mon 4/2/07 | Wed 4/11/07 | |
curb/asphalt | 0 hrs | 0% | 8 days | Wed 3/14/07 | Fri 3/23/07 | |
stucco | 0 hrs | 0% | 14 days | Tue 3/6/07 | Fri 3/23/07 |