Mary
Black Hospital
Construction Project Status Report |
 |
| Project Name |
Interventional Radiology |
| Updated |
01-12-07 |
Week Ending |
01-12-07 |
| Triad Hospital Project # |
|
Weather |
N/A - we're inside |
| Roebuck Buildings Job# |
5264 |
Reporter |
Darryl |
| 1. General Requirements |
|
| 2. Site Construction |
N/A |
| 3. Concrete |
N/A |
| 4. Masonry |
N/A |
| 5. Metals |
N/A |
| 6. Woods & Plastics |
N/A |
| 7. Thermal & Moisture Protection |
N/A |
| 8. Doors & Windows |
All set |
| 9. Finishes |
Painting hallway and touch up what's left |
| 10. Specialties |
N/A |
| 11. Equipment |
GE equipment being installed |
| 12. Furnishings |
N/A |
| 13. Special Construction |
N/A |
| 14. Conveying Systems |
N/A |
| 15. Mechanical |
working with TAB |
| 16. Electrical |
Working with GE, finishing track lighting |
| |
| Progress Meetings |
Mike Locke on site 1-16 at 9am |
| Architect Action Items |
|
| Subcontractor Action Items |
|
| Owner Action Items |
change orders request still outstanding |
|
Cath Lab |
|
 |
|
control room |
|
 |
|
Dictation |
|
 |
|
scrub sink |
|
 |
|
break room |
|
 |
|
finished bays |
|
 |
|
Nurse station |
|
|