Roebuck Buildings Co., Inc. Project Status Report
Darryl Willard - Project Manager
864/576-6330 · dwillard@roebuckbuildings.com · www.RoebuckBuildings.com
 
Mary Black Hospital
Construction Project Status Report
 
Project Name Administration Upfit
 
Updated 12-15-06 Week Ending 12-16-06
Triad Hospital Project #   Weather N/A - we're inside
Roebuck Buildings Job# 5283 Reporter Darryl

Division Updates
1. General Requirements N/A
2. Site Construction N/A
3. Concrete Cut floor for Bathroom and patched back
4. Masonry N/A
5. Metals Putting up studs
6. Woods & Plastics Blocking as needed
7. Thermal & Moisture Protection N/A
8. Doors & Windows Frames being installed
9. Finishes Vicki, Jason, John, Mike and Brenda's office complete
10. Specialties N/A
11. Equipment N/A
12. Furnishings still moving them around
13. Special Construction N/A
14. Conveying Systems N/A
15. Mechanical Moving grills as needed
16. Electrical Roughing in

Future Items
Progress Meetings  
Architect Action Items  
Subcontractor Action Items  
Owner Action Items Move in Mike on Tuesday, Move furniture from Work room.

Project Photos
 
Conference room and bathroom

Mike's office

Conference room