 |
Mary
Black
Physician Group
Construction Project Status Report |
 |
| Project Name |
Pediatric Associates - Women's
Pavilion |
| Updated |
06-15-07 |
Week Ending |
06-15-07 |
| Triad Hospital Project # |
|
Weather |
|
| Roebuck Buildings Job# |
5329 |
Reporter |
Darryl |
| 1. General Requirements |
Demo as needed |
| 2. Site Construction |
|
| 3. Concrete |
|
| 4. Masonry |
|
| 5. Metals |
|
| 6. Woods & Plastics |
|
| 7. Thermal & Moisture Protection |
|
| 8. Doors & Windows |
as Needed |
| 9. Finishes |
Painting Started flooring on Monday,
Repairing walls |
| 10. Specialities |
|
| 11. Equipment |
|
| 12. Furnishings |
Being moved in on July 5th |
| 13. Special Construction |
|
| 14. Conveying Systems |
|
| 15. Mechanical |
as needed |
| 16. Electrical |
as needed |
| |
| Progress Meetings |
|
| Architect Action Items |
|
| Subcontractor Action Items |
|
| Owner Action Items |
|
|
Lobby |
|
 |
|
New doorway |
|
 |
|
Corner office newly painted |
|
 |
|
New exam room |
|
|
|
|
|
|